Building Safety Act

Gateways 1, 2 and 3 for higher-risk buildings

What are the building safety gateways?

The gateways are the three points at which a higher-risk building project in England is checked before it can move on. Gateway 1 is at planning, where a fire statement is submitted. Gateway 2 is building control approval from the Building Safety Regulator before work starts. Gateway 3 is the completion certificate before the building is occupied, at which the golden thread is handed over to the people who will run the building.

What happens at each gateway?

Gateway 1 applies to planning applications made since 1 August 2021 for buildings with two or more dwellings that are at least 18 metres tall or have at least seven storeys. Gateways 2 and 3 are set by the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023.

The three gateways for higher-risk building work in England.
GatewayWhenWhat is submittedWho decides, and how long
Gateway 1With the planning applicationA fire statement. The Building Safety Regulator is a statutory consultee, a role it took over from the HSE on 27 January 2026.The local planning authority
Gateway 2Before building work startsPlans, a competence declaration, construction control, change control and mandatory occurrence reporting plans, a compliance statement, the fire and emergency file, a partial completion strategy where needed, and since 1 October 2026 Building Safety Levy information (SI 2023/909 reg 4).The Building Safety Regulator: 12 weeks for a new higher-risk building, 8 weeks for work to an existing one, unless extended in writing
Gateway 3Before the building is occupiedThe agreed documents, the change control log, compliance declarations from the principal designer and principal contractor, the client's statement, and a joint statement that the golden thread has been handed over (reg 40).The Building Safety Regulator: 8 weeks (reg 41)

How long does Gateway 2 take in practice?

Starting work on a higher-risk building without approval is an offence under section 35 of the Building Act 1984. The statutory period for a new building is 12 weeks, but the regulator's data for August to October 2026 shows a median of 20 weeks for new build applications, with 95% approved. External remediation took a median of 32 weeks and internal works 30 weeks, with 1,687 applications in progress.

The government announced a fast track process and more than 100 additional staff in June 2025, and in April 2026 the regulator set a target of decisions on external remediation in under 12 weeks by December 2026.

What counts as a change during construction?

Every controlled change has to be recorded in the change control log (reg 18). A notifiable change must be notified before the work starts. A major change needs approval before it starts; regulation 26 includes changes of use, height, number of storeys, structure, stairs and escape routes, external walls, fire safety measures and common parts. The regulator has six weeks to decide (reg 22).

What has to be handed over at Gateway 3?

By completion the golden thread information must be handed to the person who will be responsible for the occupied building, with its filing structure and index kept, and the recipient has to acknowledge that it is sufficient to run the building (reg 38). The completion certificate is needed to register the building, and since 1 October 2026 it is not issued until the Building Safety Levy has been paid or a notice of no charge given.

The regulator's November 2026 data shows that no new-build project approved at Gateway 2 had yet reached Gateway 3, so the handover regime has barely been tested at scale.

Building Safety Levy: who pays and when

Gateway questions

How long does Gateway 2 take?

The statutory period is 12 weeks for a new higher-risk building and 8 weeks for work to an existing one. The Building Safety Regulator's data for August to October 2026 shows a median of 20 weeks for new build applications.

What documents are needed for Gateway 2?

Regulation 4 of SI 2023/909 requires plans, a competence declaration, a construction control plan, a change control plan, a mandatory occurrence reporting plan, a building regulations compliance statement, the fire and emergency file, a partial completion strategy where relevant, and since 1 October 2026 Building Safety Levy information.

What is a major change to a higher-risk building project?

A change listed in regulation 26 of SI 2023/909, such as a change of use, height, number of storeys, structure, stairs and escape routes, external walls, fire safety measures or common parts. It needs the regulator's approval before the work starts, and the regulator has six weeks to decide.

What happens at Gateway 3?

The client applies to the Building Safety Regulator for a completion certificate with the agreed documents, the change control log, compliance declarations and a joint statement that the golden thread has been handed over. The regulator has 8 weeks to decide, and the building cannot be registered or occupied without the certificate.

Will a single construction regulator replace the Building Safety Regulator?

The government said on 9 July 2026 that a single construction regulator will be created by primary legislation, built on the Building Safety Regulator, with implementation from 2028 subject to parliamentary time. No Bill had been introduced by November 2026.